Outgassing and Test Facility Availability

28/9/2020

 
Our outgassing (ECSS-Q-ST-70-02) test facility has seen increasing demand over the past few years and 2020 it seems is no different. The facility is currently booked until the second half of January 2021. If you are looking to book an outgassing test please contact us sooner rather than later to avoid disappointment.
Similarly our vacuum test chambers seeing an increase in demand towards the end of the year, so if you are looking to make an enquiry for an urgent test or looking to book a test for next year this is worth keeping in mind.
Picture
At the start of 2020 we took delivery of a new TVAC chamber which we had scheduled to come online mid 2020. However during the UK covid-19 response in March we undertook large scale improvements to our test house involving a new floor being poured and laid along with a complete re-wiring of the laboratory to support the additional equipment we have installed. This required a complete dismantling of all of our test chambers and equipment in order to clear the lab.
Due to this disruption, along with the increased test and manufacturing demand in the second half of the year, we have had to delay the commissioning of TVAC#3 into 2021. Work has continued on the machining of the thermal exchange plate and installation of the pumps on the chamber system. However final run-up and testing is not scheduled until the start of 2021. Once ready the additional chamber in our facility will increase throughput and reduce wait times for TVAC tests.
We would like to take this opportunity to thank all of our customers who have either been using us for years or have just found is this year. We realise being busy is a very nice problem to have right now and so we thank you for choosing us for your test work.

Comments are closed.

    TS-Space Systems News

    Categories

    All
    Aerospace Test House
    Close Match Spectrum
    Covid-19
    ECSS-Q-70-04A
    ECSS-Q-ST-70-01
    ECSS-Q-ST-70-05C
    FTIR
    GDPR
    IV Measurement
    LED Solar Simulator
    Light Sources
    Lockdown
    Low Cost Solar Simulators
    Made In Britain
    Manufacturing
    Multijunction Solar Cells
    News
    Offgassing Testing
    Opening Hours
    Outgassing Testing
    Solar Simulator Demonstration
    Solar Simulator Faq
    Solar Simulators
    Test Facilities
    Unisim Compact
    Unsim Solar Simulator
    Vacuum Bakeout
    Vacuum Chambers
    Website Policies

    Archives

    January 2022
    December 2021
    April 2021
    January 2021
    November 2020
    September 2020
    May 2020
    April 2020
    February 2020
    December 2019
    August 2019
    May 2019
    April 2019
    January 2019
    December 2018
    November 2018
    July 2018
    June 2018
    May 2018
    April 2018
    January 2018
    December 2017
    November 2017
    September 2017
    July 2017
    April 2017
    January 2017
    December 2016
    November 2016
    September 2016
    August 2016
    July 2016
    April 2016
    February 2016
    January 2016
    December 2015
    October 2015
    July 2015
    June 2015

    RSS Feed

Company

About
Products
Services

Support

Contact
Guide to Simulators
Cookie Policy
Privacy Policy
​
Terms and Conditions
Picture
© COPYRIGHT 2020. ALL RIGHTS RESERVED.